C250 Taiwan High Speed Rail Project
HOME >> Bridges - C250 Taiwan High Speed Rail Project
Location: Taichung, Taiwan
Type: Warren Truss Bridge
Length: 410m x 3
Width: 11.5m~16.5m
Steel Weight: 24,000t
Year Completed: 2004
Particulars
Due to extreme site constraints, the three bridges in parallel were erected by launching and side shifting approximately 5,500t bridge sections (2/3 of bridge length).  For safety and erection efficiency reasons, permanent steel formwork was employed underneath where the concrete slabs were to be cast.